[p49]
The International Court of Justice, composed as above,
after deliberation,
having regard to Article 48 of the Statute of the Court and to Article 37 of
the Rules of Court,
Makes the following Order:
Whereas by a letter dated September 23rd, 1958, the Ambassador of Belgium to
the Netherlands transmitted to the Registry an Application of the Belgian
Government, dated September 15th, [p 50] 1958, and signed by M. Y. Devadder
as Agent for the Belgian Government, instituting proceedings before the
Court against the Spanish State in the case concerning the Barcelona
Traction, Light and Power Company, Limited;
Whereas the Application refers to Article 36, paragraph 1, of the Statute of
the Court and to the provisions, in particular Articles 2 and 17, of the
Treaty of Conciliation, Judicial Settlement and Arbitration between Belgium
and Spain, signed at Brussels on July 19th, 1927;
Whereas the text of the Application was communicated, on September 23rd,
1958, to the Ambassador of Spain to the Netherlands;
Whereas the Ambassador of Spain to the Netherlands, the Duke of Baena, in a
letter dated October 6th, 1958, announced that he had been appointed Agent
for the Spanish Government;
The Court,
Having ascertained the views of the Parties,
Fixes as follows the time-limits for the filing of the Pleadings:
for the Memorial of the Belgian Government, June 18th, 1959;
for the Counter-Memorial of the Spanish Government, February 18th, 1960;
Reserves the subsequent procedure for further decision.
Done in French and in English, the French text being authoritative, at the
Peace Palace, The Hague, this eighteenth day of October, one thousand nine
hundred and fifty-eight, in three copies, one of which will be placed in the
archives of the Court and the others transmitted to the Belgian Government
and to the Spanish Government, respectively.
(Signed) Helge Klaestad,
President.
(Signed) S. Aquarone,
Acting Registrar. |
|