|
JUDGMENT
[1] This claim is made by two private entities. The first Claimant, Trinidad
Cement Limited, ("TCL") is a company incorporated in Trinidad and Tobago.
TCL is the parent company of seven companies incorporated in different parts
of the Caribbean. The company manufactures and sells cement.
[2] The second Claimant, TCL Guyana Incorporated, ("TGI") was incorporated
in Guyana in March 2004. Eighty per cent of TGI's shares are owned by TCL.
TGI commenced operations in Guyana in January 2007 as an importer of bulk
cement from TCL and Arawak Cement Company Limited ("Arawak"). Arawak, a
wholly owned subsidiary of TCL incorporated in Barbados, also manufactures
cement. TGI packages bulk cement at its bagging plant in Georgetown for sale
in Guyana.
[3] The Defendant is the State of Guyana, a Member State of the Caribbean
Community including the CARICOM Single Market and Economy, established
pursuant to the Revised Treaty of Chaguaramas ("the RTC").
[4] The Claimants filed a single application for special leave to institute
these proceedings against Guyana. On 15th January, 2009, this Court, having
determined that each Claimant had for that purpose sufficiently satisfied
the requirements for locus standi set out at Article 222 of the RTC, granted
special leave to the Claimants. The Claimants have filed a single
Originating Application in which various forms of relief have been claimed.
THE NATURE OF THE DISPUTE AND THE RESPECTIVE CONTENTIONS
[5] The market created by the RTC is protected in some cases by the
imposition of a common external tariff ("CET") against parallel imports from
third countries. As this Court has noted in other proceedings[FN1], the CET
is a fundamental pillar in the establishment of a Caribbean Single Market
and Economy. Its primary purpose is to encourage and promote the production
of goods within CARICOM. It is but one of a range of measures identified by
the Member States as necessary in order to strengthen the productive sector
and to accelerate the process towards making their exports internationally
competitive. An important aim of the CET is to reduce the unit cost of
production of regional producers by enabling them to increase the volume of
their sales and therefore of their production, and thus reduce the price of
their product so as to make it more competitive in the international market.
In relation to the cement industry the CET on cement not qualifying for
Community treatment was fixed at 15%. Cement of Community origin is exempt
from customs duties and charges having equivalent effect.
----------------------------------------------------------------------------------------------------------------
[FN1] TCL v The Caribbean Community [2009] CCJ 4 at [46]
----------------------------------------------------------------------------------------------------------------
[6] Part Two of Chapter Five (Trade Policy) of the RTC contains the CET
regime. The rights or benefits conferred by the CET are qualified and not
absolute in that the regime may be altered or suspended by the agency
appointed by the Community to manage it. That agency is an organ of the
Community, the Council for Trade and Economic Development ("COTED").
Suspension of the CET may also be authorised between meetings of COTED by
the Secretary- General acting on behalf of COTED. See: Articles 82 and 83 of
the RTC.
[7] The RTC was enacted into law in Guyana by the Caribbean Community Act,
2006 (No. 8). The CET has been incorporated into the municipal law of Guyana
by section 7 of the Customs Act, Cap. 82:01 of the Laws of Guyana. By the
Customs (Amendment) Act 2004 the rate of the CET applicable to building
cement from non-CARICOM sources was set at 15%.
[8] By letter dated September 22, 2006 the Minister of Finance notified the
Commissioner General of the Guyana Revenue Authority that "approval has been
granted for the removal of the customs duty on building cement imported from
outside of CARICOM... with effect from 2 October 2006for a period of one (1)
year". The removal of the CET has been extended from year to year and at the
date of the hearing of these proceedings, the CET on cement remained
suspended in Guyana.
[9] Up to the date of hearing of these proceedings Guyana had made no
application to COTED or the Secretary-General for approval of a suspension
of the CET in relation to Guyana and it is common ground that Guyana did not
obtain any such approval.
[10] As a consequence of this suspension of the CET in Guyana cement from
non- CARICOM countries such as Venezuela, Colombia and the Dominican
Republic is being imported into Guyana free from the payment of the CET.
[11] In their Originating Application the Claimants contended that the
removal of the CET by Guyana without the authorisation of COTED is a breach
of the RTC. The Claimants therefore sought from the Court principally (a) a
declaration as to breach of the RTC and violation of their entitlement to
the protection of the provisions violated; (b) a mandatory order directing
the government of Guyana to reinstate the CET on cement, and (c) damages. In
their written pleadings each Claimant presented distinct claims for damages.
TGI claimed damages for lost profits allegedly suffered by it as a result of
the unlawful removal of the CET from January 2007 to date.
[12] TCL claimed for consequential loss. Included in such loss was loss of
income in its capacity as a major shareholder in TGI. Because it was an 80%
shareholder in TGI, TCL alleged that it was entitled to be paid 80% of the
profits lost by TGI. TCL also claimed that as a result of the non-
implementation of the CET one of their ships was forced to be kept idle for
a total number of 108 days over the period 2007-2008 and that it should be
compensated by Guyana for those 108 lost days. The Claimants also sought
from the Court an award of exemplary damages. In support of these claims,
the Claimants relied on the cases of Francovich[FN2], ex parte Factortame[FN3]
and Brasserie du Picheur[FN4].
----------------------------------------------------------------------------------------------------------------
[FN2] [1991] ECR 1-5357
[FN3] [1999] 3 WLR 1062
[FN4] [1996] ECR 1-1029
----------------------------------------------------------------------------------------------------------------
[13] In the course of the oral hearing TCL abandoned its claim for
consequential loss. The claim for the loss of 80% of the TGI loss was
discontinued on the basis that such a claim would amount to "double counting."
The claim for the lost days of the ship was similarly abandoned.
Interestingly, during the course of the proceedings, TCL admitted that it
had not itself suffered any direct loss as a result of Guyana's suspension
of the CET as it had sold all the cement it was able to produce during the
relevant period. In the words of one of their witnesses, "Some was sold to
St. Maarten, some to Haiti and elsewhere". For what it is worth, no evidence
was presented either that cement from Arawak, which could possibly have been
sold in Guyana during the relevant period, went unsold because of the
absence of the CET on cement in Guyana. The claims for damages which the
Court was therefore required to adjudicate were restricted to TGI's claim
for lost profits and the claim of the Claimants for exemplary damages.
[14] In its defence and written submissions Guyana stoutly denied liability.
Guyana relied on Article 179 (abuse of dominant position) and Article 184 (promotion
of consumer interests in the Community) as a defence to the claim. Guyana
also denied that the act of unilaterally suspending the CET had caused the
alleged loss. Guyana further contended that the Claimants had not
demonstrated a causal link between the actions of Guyana and the alleged
loss.
[15] Guyana submitted that since the Claimants were claiming pure economic
loss they were required to prove the right and the breach with sufficient
particularity and they had not done so. Further, the quantification of the
losses was based on speculative assumptions and expectations as to the size
of the market in Guyana and the quantities of cement imported from
non-CARICOM sources.
[16] These contentions were bolstered by reference to unreliability and
uncertainty of TCL's supply of cement to the Guyana market since 2001. Twice
in 2001 Guyana had sought and obtained approval for suspending the CET from
COTED. In September 2006 the OECS States, Suriname and Trinidad and Tobago
had been authorised to suspend the CET. Extensive flooding in Guyana in 2005
had led to increased construction activity and an anticipated sharp rise in
the demand for cement in Guyana. Some fifteen hotels as well as lodging
houses were being built to accommodate visitors expected to attend the
Cricket World Cup matches in 2007. New cricket stadia were under
construction. In short there was a boom in construction activity, which
required cement in quantities TCL could not supply and at prices that were
competitive.
[17] On the first morning of the oral hearing the Court acceded to an
application by the Claimants to strike out those paragraphs of the
submissions of Guyana that alleged predatory pricing and abuse by the
Claimants of their dominant position in the regional cement market. In so
far as predatory pricing was concerned it was a new allegation made for the
first time in Guyana's submissions in reply. More significantly however, the
Court noted that such issues would be more appropriately and effectively
investigated by a national Fair Trading Board or the regional Competition
Commission. The allegations as to abuse of dominant position were irrelevant
to the issues in this case as, even if proved, they were incapable of
excusing a breach of the obligation undertaken by Guyana under the RTC or of
relieving Guyana of any liability it may have incurred as a result of such a
breach. At an early stage of the oral hearing therefore allegations of
anti-competitive conduct ceased to form part of these proceedings.
[18] Further, the various pleaded defences were superseded when, early in
the oral hearing, counsel for Guyana in answer to a question from the Bench,
said: " We take the position that we are in breach of the Treaty and are not
trying to justify that breach, but advance this in explanation and
mitigation of our breach".
[19] As a result of this concession the character of the dispute was
transformed. The issues in the case turned mainly on proof of the loss
claimed by the Claimants and its causal connection with the unilateral
suspension of the CET without the approval of COTED or the Secretary-General.
Ultimately the main thrust of the defence was that the Claimants had failed
to prove with clarity and specificity any link between the breach of the RTC
and their alleged loss. The quantification of the losses claimed, it was
alleged, was unreliable. Guyana contended that the CET on cement had never
been implemented during the existence of TGI (which only commenced
operations in 2007) with the result that there was no previous history of
total supply of the Guyana cement market from which one could derive the
alleged loss of sales in the deregulated market.
[20] At the oral hearing, the Claimants called three witnesses in support of
their claim, namely: Mr Parasram Heerah, the Finance Manager of TCL; Mr.
Egwin Daniel, the General Manager of International Business and Marketing of
TCL, and Mr. Mark Bender, the Plant Manager of TGI. The State of Guyana
called two witnesses, namely: Mr. Neville Totaram, Technical Co-ordinator of
the National Advisory Committee on External Negotiations and Mrs. Kim
Stephen, Director of Foreign Trade in the Ministry of Tourism, Industry and
Commerce.
ADMISSIBILITY OF THE CLAIM
[21] As previously indicated, the Court had before it a single Originating
Application. In light of this, it was sufficient for the Court to satisfy
itself of its jurisdiction if only one of the Claimants satisfied the
requirements of Article 222[FN5]. As to the ability of the First Claimant so
to do, the recent judgment of the Court in an application by TCL made
against the Community[FN6] is germane. The Court stated then at [18] as
follows:
"It is not challenged that TCL is a producer of cement; that TCL supplies
cement throughout the region; that the maintenance of the CET on cement
yields a direct benefit to TCL and that decisions to suspend or lower the
CET on cement will have a prejudicial impact on that company. In light of
the foregoing, the Court holds that TCL has satisfied fully the relevant
provisions of Article 222. The Court has jurisdiction in this case and the
claim is admissible."
----------------------------------------------------------------------------------------------------------------
[FN5] See also Comite International de la Rayonne et des Fibres Synthetiques
and others v Commission of the European Communities [1993] ECR I-1125
[FN6] See TCL v The Caribbean Community [2009] CCJ 4 (OJ)
----------------------------------------------------------------------------------------------------------------
[22] The Court adopts the same reasoning here and holds that TCL has
sufficiently established the admissibility of the claim and there is
therefore no need to consider the independent position of TGI.
THE CORE ISSUES
After the meltdown of the claim and defence described above the following
emerged as the core issues in the case:
(1) Can Guyana be liable in damages for its breach of the RTC?
(2) Is TGI entitled to damages for such economic loss (loss of profits) as
it has suffered as a result of Guyana's unauthorised suspension of the CET
from 2007 to date? If so, what is the quantum of that loss?
(3) Is the remedy of exemplary damages available to the Claimants?
(4) Is declaratory relief sufficient to vindicate the Claimants' Treaty
rights? Does this Court have the power to make a mandatory order against
Guyana? If so, should it make such an order?
STATE LIABILITY AND DAMAGES FOR BREACH OF THE RTC
[24] The RTC contains no specific provisions dealing with sanctions for
breaching its provisions. A similar situation obtained in the European
Community where as well, no specific provisions existed dealing with
sanctions for breaching the provisions of the EC Treaty. In the cases C-6
and 9/90 Francovich v Italy[FN7] the applicants commenced an action against
Italy for failure to implement a directive on the protection of employees in
the event of the insolvency of their employer. The ECJ ruled that the
principle of State liability was inherent in the new legal system created by
the EEC Treaty. The ECJ based its ruling on two grounds: the principle of
effectiveness and Article 5 EC (equivalent to Article 9 of the RTC). The ECJ
stated the principle of full effectiveness in the following words:
"(33) The full effectiveness of Community rules would be impaired and the
protection of the rights which they grant would be weakened if individuals
were unable to obtain redress when their rights are infringed by a breach of
Community law for which a Member State can be held responsible.
(34) The possibility of obtaining redress from the Member State is
particularly indispensable where, as in this case, the full effectiveness of
Community rules is subject to prior action on the part of the State and
where, consequently, in the absence of such action, individuals cannot
enforce before the national courts, the rights conferred upon them by
Community law.
(35) It follows that the principle whereby a State must be liable for loss
and damage caused to individuals as a result of breaches of Community law
for which the State can be held responsible is inherent in the system of the
Treaty."
----------------------------------------------------------------------------------------------------------------
[FN7] [1991] ECR-1-5357
----------------------------------------------------------------------------------------------------------------
[25] As to the second ground for the ECJ's decision in Francovich, Article 5
EC required Member States "to take all appropriate measures" to ensure the
carrying out of obligations under the Treaty, one of which was the
obligation to nullify the unlawful consequences of a breach of Community
law. Article 5 is almost identical to Article 9 of the RTC which requires
Member States to:
"...take all appropriate measures, whether general or particular, to ensure
the carrying out of obligations arising out of this Treaty or resulting from
decisions taken by the Organs and Bodies of the Community. They shall
facilitate the achievement of the objectives of the Community. They shall
abstain from any measures which could jeopardise the attainment of the
objectives of this Treaty".
[26] Although the principle in Francovich was applied in circumstances where
there was a directive without direct effect, that principle was later
applied to the breach of Article 30 of the EEC Treaty on free movement of
goods and of Article 52 of the EEC Treaty on freedom of establishment. See:
Brasserie du Pecheur SA v Germany and R v Secretary of State for Transport
ex parte Factortame Ltd[FN8].
----------------------------------------------------------------------------------------------------------------
[FN8] Joined Cases C-46/93 and C-48/93, [1996] ECR I-1029
----------------------------------------------------------------------------------------------------------------
[27] This Court holds that a similar principle applies under the RTC and
that the new Single Market based on the rule of law implies the remedy of
compensation where rights which enure to individuals and private entities
under the Treaty are infringed by a Member State. But State liability in
damages is not automatic. A party will have to demonstrate that the
provision alleged to be breached was intended to benefit that person, that
such breach is serious, that there is substantial loss and that there is a
causal link between the breach by the State and the loss or damage to that
person.
[28] The reason for laying down conditions as to liability in damages is to
prevent States from being harassed by claims for technical breaches or minor
procedural defects. The range of potential breaches by a Member State may
extend from minor breaches to flagrant and contumacious abuses of State
power. The threshold for eligibility for damages is therefore a high one. It
is not every infringement that would attract damages. The Court may not
consider making a monetary award for minor breaches of the RTC. The breach
must be sufficiently serious to warrant the award of damages.
[29] In considering State liability for damages the Court may have regard to
any excuses or justification advanced by the State. In this regard the
evidence of witnesses for Guyana was startling. Mr. Neville Totaram,
Technical Co¬ordinator of the National Advisory Committee on External
Negotiations, said in cross-examination that he did not know why the
government of Guyana had refused to reinstate the CET. Nor could he say why
no application had been made for authorisation to suspend the CET when
waivers were being granted frequently to a number of CARICOM States.
Accordingly this Court was not required to consider the effect of such
excuses or justifications on State liability in this case.
[30] As to the sufficiency of the seriousness of the breach by Guyana, there
was evidence that:
(a) Guyana had ignored and failed to entertain repeated requests by the
Claimants' representatives to reconsider its position and to implement the
CET;
(b) Guyana had also ignored the fact that COTED, as indicated in the Minutes
of the Meeting of November 2007, had noted and recorded Guyana's failure to
regularise its position and implement the CET;
(c) Guyana was itself at all times fully aware that it was in breach of the
treaty;
(d) Notwithstanding the admission by Guyana to the Court at the hearing for
Special Leave in these proceedings that it was in breach, that State had
taken no steps to remedy the breach.
[31] In the circumstances the Court has little difficulty in concluding that
Guyana's breach in this case is sufficiently serious to warrant the award of
damages. Provided that TGI can satisfy the other conditions for being
awarded damages the Court holds that this is a case that warrants the award
of damages.
ENTITLEMENT OF TGI TO DAMAGES
[32] The Claimants presented to the Court evidence of varying quality to
explain and justify the quantum of damages being sought by TGI in these
proceedings. Logically, however, the Court must first assess the matter of
entitlement to damages. That assessment, in this case, is made against the
background that, as previously indicated, the TCL cement manufacturing plant
in Trinidad and Tobago suffered no loss as a result of Guyana's illegal
removal of the CET on cement. The evidence presented to the Court was that
notwithstanding the situation in Guyana, TCL still managed to sell all the
cement it could produce without making a loss on cement that might otherwise
have been shipped to Guyana - at least no such loss was alleged. Dr Denbow
regarded that circumstance as being entirely irrelevant to TGI's entitlement
to and its claim for, damages. The TGI claim for damages, he insisted, stood
on its own.
[33] The Court does not doubt that TGI lost the opportunity of increasing
its level of sales as a result of the illegal conduct of Guyana. It is a
cardinal principle, however, that suffering loss is not enough to ground a
case in damages against a Member State or the Community before this Court.
To be successful in its claim for damages in this Court TGI had first to
demonstrate that its losses were incurred in circumstances that rendered
them sufficiently proximate to the precise breach in question. A reduced
flow of TCL cement into Guyana might result in financial loss to various
enterprises concerned in one way or another with the importation, marketing,
sale and delivery of TCL cement in Guyana, but such enterprises would not
necessarily be able to sustain a claim for damages against the Government of
Guyana if the reduction in the flow was due to an unauthorised suspension of
the CET on cement.
[34] Since the right or benefit conferred on a Contracting Party by the
imposition of the CET under Articles 82 and 83 of the Treaty clearly enures
directly to the benefit of persons who are producers of the commodity in
respect of which the CET is imposed, it is easier for such entities
successfully to claim damages for a breach of Articles 82 or 83. What is not
so clear is whether claims for damages may in special circumstances be made
successfully by other persons such as importers of the commodity in question
and if so, what precisely those circumstances might be. It is not necessary,
however, for the Court fully to explore that issue now. It is sufficient to
state that on the facts in this case no special circumstances have been
proved which would serve to establish the requisite degree of proximity
between Guyana's breach of the treaty and such loss as TGI claims to have
suffered as a result.
EXEMPLARY DAMAGES
[35] The concept of exemplary damages is a peculiar creature of the common
law. McGregor on Damages[FN9] describes compensatory and exemplary damages
at common law as follows at paragraph 11-001:
"The primary object of an award of damages is to compensate the claimant for
the harm done to him; a possible secondary object is to punish the Defendant
for his conduct in inflicting that harm. Such a secondary object can be
achieved by awarding, in addition to the normal compensatory damages,
damages which are variously called exemplary damages, punitive damages,
vindictive damages or even retributory damages, and comes into play whenever
the Defendant's conduct is sufficiently outrageous to merit punishment, as
where it discloses malice, fraud, cruelty, insolence or the like. Whether a
modern legal system should recognise exemplary damages at all has been much
debated, but it is thought that all in all, the case for dispensing with
them is made out. The central argument against them is that they are
anomalous in the civil sphere...".
----------------------------------------------------------------------------------------------------------------
[FN9] Sweet & Maxwell, 2003, 17th edn
----------------------------------------------------------------------------------------------------------------
[36] The weight of academic and judicial opinion is that international law
has not accepted as one of its principles the concept of punitive damages:
see separate concurring opinion of Professor Orrego Vicuna in Re Letelier
and Moffitt[FN10] and the Lusitania claims[FN11].
----------------------------------------------------------------------------------------------------------------
[FN10] 88 ILR 727
[FN11] (1923), RIAA vii.32
----------------------------------------------------------------------------------------------------------------
[37] In Velasquez Rodriguez[FN12], the Inter-American Court refused to award
punitive damages, although the case involved human rights violations of a
serious nature and the Inter-American Commission had invited the Court to
consider them.
----------------------------------------------------------------------------------------------------------------
[FN12] Judgment of 21 July 1989, 95 ILR 232
----------------------------------------------------------------------------------------------------------------
[38] In the International Law Commission's Draft Articles on State
Responsibility for Internationally Wrongful Acts (2001) the introductory
commentary on Chapter III states as follows:
"...the award of punitive damages is not recognized in international law
even in relation to serious breaches of obligations arising under peremptory
norms. In accordance with article 34, the function of damages is essentially
compensatory".
[39] It is accepted, however, that there may be instances in which
international tribunals have awarded "covert punitive damages, disguised as
liberally calculated compensation for immaterial harm"[FN13]. Significantly,
however, the avowed purpose of such relief is to augment compensatory
damages awarded and not to provide a distinct and separate head of relief.
----------------------------------------------------------------------------------------------------------------
[FN13] See an article by Professor Christian J, Tams in (2002) 13 EJIL 1161,
1170
----------------------------------------------------------------------------------------------------------------
[40] Counsel for the Claimants cited the case of R v Secretary of State for
Transport, ex parte Factortame[FN14] in support of the applicability of
exemplary damages in the context of a regional economic treaty. However,
Factortame really dealt with the direct effect of a directive of the
European Commission in municipal law in a national court which was free to
award municipal damages. The European Court of Justice has never granted
such damages but leaves it to the discretion of the national court if
permissible under its national law.[FN15] In all the circumstances, the
Court is not persuaded that exemplary damages may be awarded by it and in
this case shall not award any such damages.
----------------------------------------------------------------------------------------------------------------
[FN14] [1999] 3 WLR 1062 (HL)
[FN15] Manfredi v LloydAdriatico Assicurazoni SpA [2006] 5 CMLR 17
----------------------------------------------------------------------------------------------------------------
REMEDIES FOR THE BREACH OTHER THAN DAMAGES
[41] Counsel for Guyana, Professor Massiah, rightly conceded that Guyana was
in breach of Articles 82 and 83 of the RTC. In some cases the pronouncement
of a declaration may be enough to vindicate the inherent value of the Treaty
rights contravened. But in others a simple declaration would not be enough
in light of the nature and gravity of the breach. Counsel for the Claimant
invited the Court to make a mandatory order that Guyana re-impose and
maintain the CET.
[42] This Court has held in TCL v The Caribbean Community [2009][FN16] that
it has the power to make coercive orders against Member States and the
Community: See especially [42] and [43]. In that case the Court stated:
"(42)...as to possible remedies, it must be borne in mind that the Agreement
establishing the Court has been incorporated into the domestic law of each
of the CARICOM Member States. Pursuant to the Agreement and the RTC, the
Court has power to prescribe interim measures. See: Article 218 of the RTC
and Article XIX of the Agreement. Article XV of the Agreement states that
Member States, Organs, Bodies of the Community or persons to whom a judgment
of the Court applies, shall comply with that judgment. Further, Article XXVI
of the Agreement enjoins all the Contracting Parties to ensure that all
authorities of a Contracting Party act in aid of the Court and that any
judgment, decree, order, sentence of the Court given in exercise of its
jurisdiction shall be enforced by all courts and authorities in any
territory of the Contracting Parties as if it were a judgment, decree, order
or sentence of a superior court of that Contracting Party.
(43) Given the Court's duty to enforce the rule of law and to render the RTC
effective, competence to review the legality of acts adopted by Community
institutions must perforce include competence to award appropriate relief to
private entities that have suffered and established loss as a result of an
illegal act or omission on the part of the Community. If the Court were
restricted to the issuance of mere declarations, none of the enforcement
mechanisms referred to in the previous paragraph would have been required.
In the judgment of the Court, coercive remedies are therefore available to
the Court."
----------------------------------------------------------------------------------------------------------------
[FN16] Supra at footnote 1.
----------------------------------------------------------------------------------------------------------------
[43] In the instant case the Court accepts that a waiver of the CET in 2006
may have been prompted by a fitful, unreliable supply of cement by TCL. What
has not been explained is the persistent refusal by Guyana to seek the
sanction of COTED. None of the witnesses called by Guyana could explain the
continued unwillingness or refusal by Guyana to honour its treaty
obligations by seeking the prior approval of COTED. This flagrant breach has
been persisted in throughout the pleadings down to the commencement of the
hearing. Counsel had no instructions from his client to give an undertaking
that the breach would be brought to an end and the CET implemented and
maintained in accordance with Articles 82 and 83 of the RTC. In those
circumstances there would be grave consequences for the rule of law in the
CARICOM Single Market if a coercive order were not made. Accordingly the
Court orders Guyana to re-impose the CET within 28 days of the date of this
order and to maintain it thereafter until and unless a suspension is
authorised by COTED or the Secretary-General pursuant to Article 83.
ORDERS OF THE COURT
[44] The Court declares that Guyana has since October 2006 been in breach of
the provisions of Article 82 of the RTC by failing to implement and maintain
the CET. The Claimants are entitled to the benefit of having the CET
maintained by Guyana subject to Guyana's right to make an application to
COTED or the Secretary-General pursuant to Article 83 of the RTC.
[45] The Court further orders Guyana within 28 days of the date of this
order to implement and thereafter maintain the CET in respect of cement from
non- CARICOM sources. This is without prejudice to Guyana's right to make an
application to COTED or the Secretary-General under Article 83 of the RTC.
The parties are to have liberty to apply to the Court in respect of any
matters arising out of this mandatory order.
[46] Guyana is ordered to pay two-thirds of the Claimants' costs, to be
taxed if not agreed. |
|